Quote Comparison

Compare on scope, not headline price

Quotes are normalised against the same scope so exclusions and allowances are visible before a supplier is chosen.

AI recommendation

Confidence 91%

Adelaide Concrete Co. at $68,900 is the best overall value.

Southern Slabs is $7,500 cheaper on paper but excludes cut and fill and pump hire, both of which are required on this site.

  • Adelaide Concrete Co. is the only fully scoped quote — cut and fill and pump hire are priced, not excluded.
  • Adjusted for the excluded items, Southern Slabs lands between $73,500 and $76,000, above the recommended quote.
  • 14-day lead time is the only option that holds the current slab pour date.
  • GST position is stated clearly; Southern Slabs does not state a GST position and needs clarification.

RFQ-1041 · Concrete · Greenwood Villa

3 quotes analysed
CriterionSouthern SlabsLowest priceAdelaide Concrete Co.AI recommendedTorrens Civil
Total$61,400$68,900$71,250
GST positionNot stated — needs clarificationInclusive of GSTInclusive of GST
Included
  • Slab supply and pour
  • Reinforcement mesh
  • Standard formwork
  • Slab supply and pour
  • Reinforcement
  • Cut and fill
  • Pump hire
  • Waffle pods
  • Full slab scope
  • Cut and fill
  • Pump hire
  • Rock excavation to 600mm
Excluded
  • Cut and fill
  • Concrete pump hire
  • Rock excavation
  • Rock excavation beyond 300mm
  • Retaining walls
AllowancesSand fill $2,800Rock excavation contingency $3,000None
Lead time21 days14 days25 days
Quote validity14 days30 days21 days
Payment terms50% deposit, balance on completionNet 30 from invoiceProgress claims, net 14
Missing information
  • No GST position stated on the quote
  • No confirmed pour date
Complete
  • Programme dates not provided
Risk flags
  • Cut and fill excluded — likely $6,000–$9,000 additional on this site
  • Pump hire excluded and required for the rear pour
  • Rock excavation beyond 300mm charged at day rate
  • 25-day lead time does not suit the current programme
AI confidence62%91%84%
StatusReceivedReceivedReceived
Actions

Before approval

  • Confirm the GST position on any quote that does not state one.
  • Price the excluded cut and fill and pump hire before comparing totals.
  • Check the lead time against the current slab pour date.
Aamico AI Operating System — interactive demonstration. All operational data shown is synthetic.Viewing: This week · /procurement/quotes