Executive summary

This week · all projects

This week: 3 projects need attention, 3 RFQs are awaiting supplier responses and 4 decisions are waiting on you.

  • Greenwood Villa frame stage carries the largest schedule exposure
  • Estimating is the constrained function; the site supervisor has spare capacity
  • Unapproved variation value is sitting against project margin

Projects at risk

3 of 4
  • Greenwood VillaFrame · 3 days · forecast 19 Nov 2026Delayed
  • Prospect CourtSlab · 4 days · forecast 9 Dec 2026At risk
  • Henley GrovePre-construction · 0 days · forecast 12 Feb 2027Awaiting approval

Staff capacity

Utilisation this week
  • Daniel WhitcombeSite Supervisor31%
  • Priya RamanEstimator91%
  • Tom ElleryDraftsperson76%
  • Sarah KaurAdministrator71%
  • Michael TohSales / Client Consultant66%

Procurement bottlenecks

  • 3 RFQs are awaiting supplier responses, holding up trade starts.
  • 3 quotes are ready for comparison and decision.
  • 1 purchase orders are sitting in exception.

Decisions required

Human decision required
  • Flooring variation — Greenwood VillaVAR-1017 · $5,400 · margin impact 1.1%
  • Purchase order — Gulf Plumbing ServicesPO-2208 · $31,200 ex GST · Greenwood Villa
  • Revised schedule — Greenwood Villa frameThree-day variance · forecast completion 19 Nov
  • Assign a third site to Daniel Whitcombe27 hours unallocated this week

Variations and margin impact

$6,800 unapproved
  • VAR-1017Upgrade to European oak engineered timber flooring$5,400 · -1.1%
  • VAR-1014Additional external power points (3)$1,150 · -0.2%
  • VAR-1019Feature cladding to front facade$1,400 · -0.3%

Work completed by AI

Last 24 hours
  • Detected a three-day variance on the Greenwood Villa frame stage (Schedule monitor)
  • Analysed three concrete quotes and normalised inclusions for RFQ-1041 (Quote comparison)
  • Prepared follow-up reminders for five suppliers on RFQ-1048 (RFQ workspace)
  • Updated supervisor capacity from site check-ins and task logs (Capacity monitor)
  • Flagged a client selection inconsistent with the signed allowance (Selections monitor)
  • Refreshed the weekly director brief (Director reports)

Recommended priorities for next week

  1. 1. Approve the Greenwood Villa recovery plan and confirm the revised roofing sequence.
  2. 2. Close out the outstanding concrete RFQ so the Prospect Court slab date can be locked in.
  3. 3. Rebalance site supervision by assigning a third site.
  4. 4. Clear the pending variations before supplier orders are placed.

AI recommendation: Priorities: approve the Greenwood recovery plan, clear the four pending decisions, and rebalance site supervision.