Projects & Delays
Golden Grove, SA · the Nguyen family
Greenwood Villa
17-week programme · contract value $486,000 · supervisor Daniel Whitcombe
Delayed
Construction programme
Week 1 – 17- Site start & set-out
- Footings
- Slab
- Frame
Three days behind — truss delivery arrived late
- Roofing
- Lock-up
- Fixing
- Wet areas & paint
- Handover
Complete In progress At risk Not started
Frame stage is 3 days behind
HighTruss delivery arrived two days late and the frame crew lost a day to weather.
Downstream impact
- Roofing start pushes from 18 Jul to 21 Jul
- Lock-up milestone moves out by three days
- Practical completion forecast moves to 19 Nov
AI recommendation: Approve a revised schedule that compresses roofing by two days using the second crew, and notify the site supervisor today.
Activity & communications
AI detected a three-day variance on the frame stage
Schedule monitor · Today 07:42
Truss delivery confirmed for Thursday
Supplier email · Yesterday
Supervisor logged frame progress at 60%
Buildertrend · 2 days ago
Position
Current stage
Frame
Progress
42%
Scheduled
14 Nov 2026
Forecast
19 Nov 2026
Variance
3 days
Next milestone
Frame inspection
Milestones
- Slab inspection12 Jun Complete
- Frame inspection3 Jul Overdue
- Roof cover18 Jul Scheduled
- Lock-up8 Aug Scheduled
Procurement
Linked records- RFQ-1052 · RoofingResponses in
- RFQ-1041 · ConcreteResponses in
- PO-2208 · PlumbingPending approval
Selections & variations
Linked records- FlooringDiscrepancy
- Kitchen benchtopsApproved
- VAR-1017 · $5,400Awaiting approval