Prospect, SA · the Alvarez family

Prospect Court

17-week programme · contract value $528,000 · supervisor Daniel Whitcombe

At risk

Construction programme

Week 1 – 17
  • Site start & set-out
  • Footings
  • Slab

    Concrete supplier has not confirmed the pour date

  • Frame
  • Roofing
  • Lock-up
  • Fixing
  • Wet areas & paint
  • Handover
Complete In progress At risk Not started

Slab stage is 4 days behind

Medium

Concrete supplier has not confirmed a pour date; RFQ responses are outstanding.

Downstream impact

  • Frame start slips four days
  • Forecast completion moves to 9 Dec

AI recommendation: Escalate RFQ-1048 with a follow-up to the five non-responding suppliers.

Activity & communications

  • Concrete RFQ responses outstanding from five suppliers

    Procurement monitor · Today 08:10

  • Working drawings revision C issued

    OneDrive · Yesterday

Position

Current stage

Slab

Progress

24%

Scheduled

4 Dec 2026

Forecast

9 Dec 2026

Variance

4 days

Next milestone

Slab pour

Milestones

  • Footing inspection24 Jun Complete
  • Slab pour9 Jul Due
  • Frame start22 Jul Scheduled

Procurement

Linked records

Selections & variations

Linked records
Synthetic demonstration data